This table provides an overview of the physical and technical capacity at every Grid Supply Point (GSP).
The Technical
Limits fields provide a RAG status on whether this is available yet, and where available the limits as agreed with National Grid ESO which will not have a negative impact on the transmission network. This is an ongoing development and as they become available more GSPs will become part of this process, and values
may change over time.
The Import limit is provided for winter, summer and the access period. The Historical Maximum and Minimum Power Flow comes from UK Power Networks' own analysis of the power flow through that GSP in the previous year.
The Asset Import Limit and Asset Export Limit is calculated based on the Supergrid transformer capacities available at the GSP, and are provided for indicative purposes only and may not reflect the actual capacity at the GSP.
The Export and Import Capacity Utilisation is then calculated as a ratio of the maximum and minimum demand and the capacity at the GSP, which where possible is the technical limits and where not possible, the asset capacity. Combined with the
previous table it provides a thorough view of headroom at all GSPs.
Methodological Approach
Data is compiled from existing datashare between UK Power Networks and the National Energy System Operator. UK Power Networks has included Functional Locations (FLOCs) to aid with referencing with other UK Power Networks datasets.
Quality Control Statement
Quality Control Measures include:
Verification steps to match features only with confirmed functional locations.
Manual review and correct of data inconsistencies
Use of additional verification steps to ensure accuracy in the methodology
Assurance Statement
The Open Data Team and DSO Data Science team worked together to ensure data accuracy and consistency.